BetaActiveWindBHPLBNL
200 MW generation in Campbell, SD · In queue since August 2022 · Proposed COD November 2025
200 MW
Capacity
1
Components
Wind
3y 7m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
4 months past proposed COD
Construction75%
Queue EntryAug 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-11-30
Project Details
State
SD
County
Campbell
Region
West
Developer
—
Utility
Black Hills Power
Entity
BHP
Point of Interconnection
Pumpkin Buttes - Donkey Creek 230 kV line
Data Source
LBNL