BetaActiveSolarBHPLBNL
250 MW generation in Dawes, SD · In queue since July 2022 · Proposed COD December 2025
250 MW
Capacity
1
Components
Solar
3y 8m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 5m
Schedule
4 months past proposed COD
Construction75%
Queue EntryJul 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
SD
County
Dawes
Region
West
Developer
—
Utility
Black Hills Power
Entity
BHP
Point of Interconnection
West Hills - Stegall 230 kV line
Data Source
LBNL
No news available for this project.