— Project Summary

Queue ID
BHP-BHBE G17
Capacity
200 MW
Technology
Wind
Status
active
Location
Campbell, WY
Region
West
Developer
IA Status
IA Executed

BetaActiveWindBHPLBNL

200 MW generation in Campbell, WY · In queue since March 2022 · Proposed COD December 2026

200 MW

Capacity

1

Components

Wind

4 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 9m

Construction75%
Queue EntryMar 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

WY

County

Campbell

Region

West

Developer

Utility

Black Hills Power

Entity

BHP

Point of Interconnection

Pumpkin Buttes - Windstar Tap

Data Source

LBNL

No news available for this project.