BetaActiveWindBHPLBNL
200 MW generation in Campbell, WY · In queue since March 2022 · Proposed COD December 2026
200 MW
Capacity
1
Components
Wind
4 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 9m
Construction75%
Queue EntryMar 22, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
WY
County
Campbell
Region
West
Developer
—
Utility
Black Hills Power
Entity
BHP
Point of Interconnection
Pumpkin Buttes - Windstar Tap
Data Source
LBNL
No news available for this project.