290 MW generation in Campbell, WY · In queue since December 2021 · Proposed COD November 2024
290 MW
Capacity
1
Components
Wind
4y 3m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 11m
Schedule
17 months past proposed COD
Construction75%
Queue EntryDec 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2024-11-15
Project Details
State
WY
County
Campbell
Region
West
Developer
—
Utility
Black Hills Power
Entity
BHP
Point of Interconnection
Pumpkin Buttes - Windstar Tap
Data Source
LBNL