300 MW generation in Custer, NE · In queue since July 2017 · Proposed COD December 2023
300 MW
Capacity
1
Components
Wind
8y 8m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 5m
Schedule
27 months past proposed COD
Construction75%
Queue EntryJul 5, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
NE
County
Custer
Region
West
Developer
—
Utility
Black Hills Power
Entity
BHP
Point of Interconnection
West Hill - Stegall Tap
Data Source
LBNL