— Project Summary

Queue ID
BHCT-BHCT G52
Capacity
100 MW
Technology
Solar
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBHCTLBNL

100 MW generation in Pueblo, CO · In queue since June 2024 · Proposed COD December 2026

100 MW

Capacity

1

Components

Solar

1y 9m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 6m

Impact Study25%
Queue EntryJun 14, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Black Hills Colorado Electric

Entity

BHCT

Point of Interconnection

Division of Transportation 115 kV substation

Data Source

LBNL

No news available for this project.