BetaActiveBatteryBHCTLBNL
50 MW storage in Pueblo, CO · In queue since June 2024 · Proposed COD March 2026
50 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 9m
Schedule
1 months past proposed COD
Impact Study25%
Queue EntryJun 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
CO
County
Pueblo
Region
West
Developer
Black Hills Colorado Electric, LLC
Utility
Black Hills Colorado Electric
Entity
BHCT
Point of Interconnection
a Substation, Approximate Coordinates: 38.3188659, -
Data Source
LBNL
No news available for this project.