BetaActiveSolarBatteryBHCTLBNL
80 MW hybrid in Pueblo, CO · In queue since August 2022 · Proposed COD December 2026
80 MW
Capacity
1
Components
Solar
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 4m
In Study38%
Queue EntryAug 9, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Black Hills Colorado Electric
Entity
BHCT
Point of Interconnection
Boone - Nyberg 115 kV Line
Data Source
LBNL
No news available for this project.