— Project Summary

Queue ID
BHCT-BHCT G32
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBHCTLBNL

200 MW hybrid in Pueblo, CO · In queue since April 2022 · Proposed COD April 2025

200 MW

Capacity

1

Components

Solar

3y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

12 months past proposed COD

In Study38%
Queue EntryApr 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Black Hills Colorado Electric

Entity

BHCT

Point of Interconnection

Burnt Mill Substation

Data Source

LBNL