BetaActiveSolarBHCTLBNL
75 MW generation in Pueblo, CO · In queue since February 2020 · Proposed COD December 2023
75 MW
Capacity
1
Components
Solar
6y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 10m
Schedule
27 months past proposed COD
In Study38%
Queue EntryFeb 27, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Black Hills Colorado Electric
Entity
BHCT
Point of Interconnection
Nyberg 115kV Substation
Data Source
LBNL
No news available for this project.