BetaActiveSolarBHCTLBNL
60 MW generation in Pueblo, CO · In queue since April 2015 · Proposed COD November 2019
60 MW
Capacity
1
Components
Solar
10y 11m
In Queue
IA Pending
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
4y 7m
Schedule
78 months past proposed COD
In Study38%
Queue EntryApr 1, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-11-01
Project Details
State
CO
County
Pueblo
Region
West
Developer
—
Utility
Black Hills Colorado Electric
Entity
BHCT
Point of Interconnection
Pueblo Airport Sub
Data Source
LBNL