— Project Summary

Queue ID
BHCT-BHCT G19
Capacity
60 MW
Technology
Solar
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status
IA Pending

BetaActiveSolarBHCTLBNL

60 MW generation in Pueblo, CO · In queue since April 2015 · Proposed COD November 2019

60 MW

Capacity

1

Components

Solar

10y 11m

In Queue

IA Pending

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

4y 7m

Schedule

78 months past proposed COD

In Study38%
Queue EntryApr 1, 2015

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-11-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Black Hills Colorado Electric

Entity

BHCT

Point of Interconnection

Pueblo Airport Sub

Data Source

LBNL