— Project Summary

Queue ID
Avista-TCS-03
Capacity
80 MW
Technology
Solar+Battery
Status
suspended
Location
Adams, WA
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryAvistaLBNL

80 MW hybrid in Adams, WA

80 MW

Capacity

1

Components

Solar

In Queue

Suspended

IA Status

Interconnection Timeline
Suspended38%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

WA

County

Adams

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Warden 115kV Station

Data Source

LBNL

No news available for this project.