— Project Summary

Queue ID
Avista-CS24-15
Capacity
300 MW
Technology
Wind+Battery
Status
active
Location
Lincoln, WA
Region
West
Developer
IA Status
Cluster Study

BetaActiveWindBatteryAvistaLBNL

300 MW hybrid in Lincoln, WA · In queue since April 2024 · Proposed COD December 2027

300 MW

Capacity

1

Components

Wind

1y 11m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntryApr 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

WA

County

Lincoln

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Bluebird Substation 230kV

Data Source

LBNL

No news available for this project.