BetaActiveSolarAvistaLBNL
70 MW generation in Whitman, WA · In queue since April 2024 · Proposed COD October 2027
70 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 6m
Impact Study25%
Queue EntryApr 30, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-26
Project Details
State
WA
County
Whitman
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Thornton 230kV
Data Source
LBNL
No news available for this project.