— Project Summary

Queue ID
Avista-CS24-09
Capacity
9.5 MW
Technology
Solar
Status
active
Location
Adams, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarAvistaLBNL

9.5 MW generation in Adams, WA · In queue since April 2024 · Proposed COD August 2025

9.5 MW

Capacity

1

Components

Solar

1y 11m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 4m

Schedule

8 months past proposed COD

Facilities Study50%
Queue EntryApr 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-08-01

Project Details

State

WA

County

Adams

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Othello 13kV

Data Source

LBNL

No news available for this project.