9.5 MW generation in Adams, WA · In queue since April 2024 · Proposed COD August 2025
9.5 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 4m
Schedule
8 months past proposed COD
Facilities Study50%
Queue EntryApr 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-01
Project Details
State
WA
County
Adams
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Othello 13kV
Data Source
LBNL