— Project Summary

Queue ID
Avista-CS24-07
Capacity
2 MW
Technology
Solar
Status
active
Location
Adams, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarAvistaLBNL

2 MW generation in Adams, WA · In queue since April 2024 · Proposed COD December 2024

2 MW

Capacity

1

Components

Solar

1y 11m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

8 months

Schedule

16 months past proposed COD

Facilities Study50%
Queue EntryApr 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-10

Project Details

State

WA

County

Adams

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Othello 13kV

Data Source

LBNL

No news available for this project.