2 MW generation in Adams, WA · In queue since April 2024 · Proposed COD December 2024
2 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
8 months
Schedule
16 months past proposed COD
Facilities Study50%
Queue EntryApr 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-10
Project Details
State
WA
County
Adams
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Othello 13kV
Data Source
LBNL
No news available for this project.