BetaActiveSolarAvistaLBNL
40 MW generation in Spokane, WA · In queue since April 2023 · Proposed COD June 2027
40 MW
Capacity
1
Components
Solar
2y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 2m
Construction75%
Queue EntryApr 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
WA
County
Spokane
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
North Fairchild Tap (115kV)
Data Source
LBNL
No news available for this project.