40 MW generation in Lincoln, WA · In queue since May 2023 · Proposed COD July 2024
40 MW
Capacity
1
Components
Solar
2y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 2m
Schedule
21 months past proposed COD
Construction75%
Queue EntryMay 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-07-01
Project Details
State
WA
County
Lincoln
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Davenport (115kV)
Data Source
LBNL