BetaActiveWindAvistaLBNL
255.9 MW generation in Whitman, WA · In queue since April 2023 · Proposed COD December 2025
255.9 MW
Capacity
1
Components
Wind
2y 11m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 8m
Schedule
3 months past proposed COD
Construction75%
Queue EntryApr 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-12-15
Project Details
State
WA
County
Whitman
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Shawnee - Thornton (230kV)
Data Source
LBNL
No news available for this project.