BetaActiveSolarBatteryAvistaLBNL
200 MW hybrid in Franklin, WA · In queue since September 2019 · Proposed COD December 2021
200 MW
Capacity
1
Components
Solar
6y 6m
In Queue
—
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 3m
Schedule
52 months past proposed COD
Pre-Study0%
Queue EntrySep 6, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
WA
County
Franklin
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Saddle Mt - Walla Walla 230 kV line
Data Source
LBNL
No news available for this project.