— Project Summary

Queue ID
Avista-97
Capacity
100 MW
Technology
Solar+Battery
Status
suspended
Location
Nez Perce, ID
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryAvistaLBNL

100 MW hybrid in Nez Perce, ID · In queue since June 2019 · Proposed COD December 2025

100 MW

Capacity

1

Components

Solar

6y 9m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

6y 6m

Suspended38%
Queue EntryJun 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

ID

County

Nez Perce

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Lolo 230 kV Station

Data Source

LBNL