BetaSuspendedSolarBatteryAvistaLBNL
100 MW hybrid in Nez Perce, ID · In queue since June 2019 · Proposed COD December 2025
100 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 6m
Suspended38%
Queue EntryJun 24, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Nez Perce
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Lolo 230 kV Station
Data Source
LBNL
No news available for this project.