— Project Summary

Queue ID
Avista-85
Capacity
5 MW
Technology
Solar
Status
active
Location
Adams, WA
Region
West
Developer
IA Status

BetaActiveSolarAvistaLBNL

5 MW generation in Adams, WA · In queue since April 2019 · Proposed COD August 2020

5 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

1y 4m

Schedule

68 months past proposed COD

Pre-Study0%
Queue EntryApr 17, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-08-31

Project Details

State

WA

County

Adams

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

SOT 522

Data Source

LBNL

No news available for this project.