BetaActiveSolarAvistaLBNL
5 MW generation in Adams, WA · In queue since April 2019 · Proposed COD August 2020
5 MW
Capacity
1
Components
Solar
6y 11m
In Queue
—
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
1y 4m
Schedule
68 months past proposed COD
Pre-Study0%
Queue EntryApr 17, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-08-31
Project Details
State
WA
County
Adams
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
SOT 522
Data Source
LBNL