— Project Summary

Queue ID
Avista-84
Capacity
5 MW
Technology
Solar+Battery
Status
active
Location
Stevens, WA
Region
West
Developer
IA Status

BetaActiveSolarBatteryAvistaLBNL

5 MW hybrid in Stevens, WA · In queue since April 2019 · Proposed COD December 2024

5 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

5y 8m

Schedule

15 months past proposed COD

Pre-Study0%
Queue EntryApr 17, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

WA

County

Stevens

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Chewelah 13kV

Data Source

LBNL

No news available for this project.