BetaActiveSolarBatteryAvistaLBNL
5 MW hybrid in Stevens, WA · In queue since April 2019 · Proposed COD December 2024
5 MW
Capacity
1
Components
Solar
6y 11m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
5y 8m
Schedule
15 months past proposed COD
Pre-Study0%
Queue EntryApr 17, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
WA
County
Stevens
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Chewelah 13kV
Data Source
LBNL
No news available for this project.