— Project Summary

Queue ID
Avista-83
Capacity
300.15 MW
Technology
Wind
Status
active
Location
Meagher, MT
Region
West
Developer
IA Status
IA Executed

BetaActiveWindAvistaLBNL

300.15 MW generation in Meagher, MT · In queue since March 2019

300.15 MW

Capacity

1

Components

Wind

7 years

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

7 years

Construction75%
Queue EntryMar 27, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MT

County

Meagher

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Future Loco Mt Station for Project #50

Data Source

LBNL

No news available for this project.