BetaActiveWindAvistaLBNL
600 MW generation in Meagher, MT · In queue since February 2019
600 MW
Capacity
1
Components
Wind
7y 1m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
7y 1m
Construction75%
Queue EntryFeb 20, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MT
County
Meagher
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Future Loco Mt Station for Project #50
Data Source
LBNL
No news available for this project.