BetaActiveSolarAvistaLBNL
1 MW generation in Lincoln, WA · In queue since October 2018 · Proposed COD August 2020
1 MW
Capacity
1
Components
Solar
7y 5m
In Queue
—
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
1y 10m
Schedule
68 months past proposed COD
Pre-Study0%
Queue EntryOct 4, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-08-15
Project Details
State
WA
County
Lincoln
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Harrington Substation 115 kV
Data Source
LBNL
No news available for this project.