— Project Summary

Queue ID
Avista-70
Capacity
2.5 MW
Technology
Battery
Status
active
Location
Spokane, WA
Region
West
Developer
IA Status

BetaActiveBatteryAvistaLBNL

2.5 MW storage in Spokane, WA · In queue since August 2018 · Proposed COD January 2019

2.5 MW

Capacity

1

Components

Battery

7y 7m

In Queue

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

5 months

Schedule

88 months past proposed COD

Pre-Study0%
Queue EntryAug 31, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-01-01

Project Details

State

WA

County

Spokane

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Liberty Lake 12F4

Data Source

LBNL

No news available for this project.