— Project Summary

Queue ID
Avista-67
Capacity
80 MW
Technology
Solar
Status
active
Location
Adams, WA
Region
West
Developer
IA Status

BetaActiveSolarAvistaLBNL

80 MW generation in Adams, WA · In queue since August 2018 · Proposed COD June 2023

80 MW

Capacity

1

Components

Solar

7y 7m

In Queue

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

4y 10m

Schedule

33 months past proposed COD

Pre-Study0%
Queue EntryAug 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-06-30

Project Details

State

WA

County

Adams

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Lind - Warden 115 kV line

Data Source

LBNL

No news available for this project.