BetaActiveOtherAvistaLBNL
71 MW generation in Stevens, WA · In queue since July 2018 · Proposed COD July 2026
71 MW
Capacity
1
Components
Other
7y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8 years
Construction75%
Queue EntryJul 10, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2026-07-01
Project Details
State
WA
County
Stevens
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Kettle Falls 115 kV Station
Data Source
LBNL
No news available for this project.