— Project Summary

Queue ID
Avista-63
Capacity
26 MW
Technology
Hydro
Status
active
Location
Kootenai, ID
Region
West
Developer
IA Status
IA Executed

BetaActiveHydroAvistaLBNL

26 MW generation in Kootenai, ID · In queue since June 2018 · Proposed COD March 2028

26 MW

Capacity

1

Components

Hydro

7y 9m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

9y 9m

Construction75%
Queue EntryJun 8, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2028-03-01

Project Details

State

ID

County

Kootenai

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Post Falls Substation

Data Source

LBNL

No news available for this project.