— Project Summary

Queue ID
Avista-60
Capacity
150 MW
Technology
Solar+Battery
Status
suspended
Location
Asotin, WA
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryAvistaLBNL

150 MW hybrid in Asotin, WA · In queue since June 2018 · Proposed COD September 2025

150 MW

Capacity

1

Components

Solar

7y 9m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

7y 3m

Suspended38%
Queue EntryJun 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-01

Project Details

State

WA

County

Asotin

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Dry Creek 230 kV station

Data Source

LBNL

No news available for this project.