0.25 MW generation in Lincoln, WA · In queue since April 2014 · Proposed COD September 2014
0.25 MW
Capacity
1
Components
Gas
11y 11m
In Queue
—
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
5 months
Schedule
140 months past proposed COD
Pre-Study0%
Queue EntryApr 10, 2014
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-09-15
Project Details
State
WA
County
Lincoln
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Avista_x0019_s distribution system near the intersection of Bourne and Doerschlag Road in Lincoln County Washington
Data Source
LBNL