BetaActiveSolarBatteryAvistaLBNL
1 MW hybrid in Spokane, WA · In queue since August 2021 · Proposed COD December 2022
1 MW
Capacity
1
Components
Solar
4y 7m
In Queue
—
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 4m
Schedule
40 months past proposed COD
Pre-Study0%
Queue EntryAug 19, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-01
Project Details
State
WA
County
Spokane
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
13.2kV Third and Hatch Feeders
Data Source
LBNL
No news available for this project.