— Project Summary

Queue ID
Avista-120
Capacity
1 MW
Technology
Solar+Battery
Status
active
Location
Spokane, WA
Region
West
Developer
IA Status

BetaActiveSolarBatteryAvistaLBNL

1 MW hybrid in Spokane, WA · In queue since August 2021 · Proposed COD December 2022

1 MW

Capacity

1

Components

Solar

4y 7m

In Queue

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 4m

Schedule

40 months past proposed COD

Pre-Study0%
Queue EntryAug 19, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

WA

County

Spokane

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

13.2kV Third and Hatch Feeders

Data Source

LBNL

No news available for this project.