560 MW hybrid in Garfield, WA · In queue since January 2021 · Proposed COD December 2025
560 MW
Capacity
3
Components
Solar + Wind + Battery
5y 2m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 11m
Schedule
4 months past proposed COD
Pre-Study0%
Queue EntryJan 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Technology
Solar100 MW · 18%
Wind275 MW · 49%
Battery185 MW · 33%
Project Details
State
WA
County
Garfield
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
DryCreek 230 kV or Walla Walla to Dry Creek 230 kV
Data Source
LBNL
No news available for this project.