— Project Summary

Queue ID
Avista-104
Capacity
120 MW
Technology
Wind
Status
active
Location
Spokane, WA
Region
West
Developer
IA Status

BetaActiveWindAvistaLBNL

120 MW generation in Spokane, WA · In queue since March 2020 · Proposed COD December 2023

120 MW

Capacity

1

Components

Wind

6 years

In Queue

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 9m

Schedule

27 months past proposed COD

Pre-Study0%
Queue EntryMar 2, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

WA

County

Spokane

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Benewah Substation 230 kV

Data Source

LBNL

No news available for this project.