BetaActiveWindAvistaLBNL
120 MW generation in Spokane, WA · In queue since March 2020 · Proposed COD December 2023
120 MW
Capacity
1
Components
Wind
6 years
In Queue
—
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 9m
Schedule
27 months past proposed COD
Pre-Study0%
Queue EntryMar 2, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
WA
County
Spokane
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Benewah Substation 230 kV
Data Source
LBNL
No news available for this project.