BetaActiveSolarAvistaLBNL
40 MW generation in Lincoln, WA · In queue since December 2019 · Proposed COD July 2021
40 MW
Capacity
1
Components
Solar
6y 3m
In Queue
—
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 7m
Schedule
58 months past proposed COD
Pre-Study0%
Queue EntryDec 10, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-07-01
Project Details
State
WA
County
Lincoln
Region
West
Developer
—
Utility
Avista Utilities
Entity
Avista
Point of Interconnection
Harrington Substation 115 kV
Data Source
LBNL