— Project Summary

Queue ID
Avista-100
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Benewah, ID
Region
West
Developer
IA Status

BetaActiveSolarBatteryAvistaLBNL

100 MW hybrid in Benewah, ID · In queue since September 2019 · Proposed COD December 2021

100 MW

Capacity

1

Components

Solar

6y 6m

In Queue

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 3m

Schedule

52 months past proposed COD

Pre-Study0%
Queue EntrySep 27, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

ID

County

Benewah

Region

West

Developer

Utility

Avista Utilities

Entity

Avista

Point of Interconnection

Benewah 230 kV Station

Data Source

LBNL