— Project Summary

Queue ID
APS-SP111
Capacity
192 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

192 MW hybrid in Pinal, AZ · Proposed COD December 2026

192 MW

Capacity

1

Components

Solar

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline
In Study38%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Thornton 69 kV SS

Data Source

LBNL