BetaActiveSolarBatteryAPSLBNL
213.75 MW hybrid in Pinal, AZ · In queue since January 2023 · Proposed COD June 2025
213.75 MW
Capacity
1
Components
Solar
3y 2m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 5m
Schedule
10 months past proposed COD
Construction75%
Queue EntryJan 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Saguaro 230kV substation
Data Source
LBNL
No news available for this project.