— Project Summary

Queue ID
APS-Q574
Capacity
220 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveBatteryAPSLBNL

220 MW storage in Maricopa, AZ · In queue since May 2024 · Proposed COD December 2028

220 MW

Capacity

1

Components

Battery

1y 10m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 7m

Impact Study25%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Lat: 33.4367050882, Long: - 112.592569119 (Buckeye 230KV Substation)

Data Source

LBNL

No news available for this project.