— Project Summary

Queue ID
APS-Q572
Capacity
1300 MW
Technology
Hydro
Status
active
Location
Riverside, CA
Region
West
Developer
IA Status
Cluster Study

BetaActiveHydroAPSLBNL

1,300 MW generation in Riverside, CA · In queue since May 2024 · Proposed COD May 2031

1,300 MW

Capacity

1

Components

Hydro

1y 10m

In Queue

Cluster Study

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

7 years

Impact Study25%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-05-09

Project Details

State

CA

County

Riverside

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Delaney 500kV Swtchyard

Data Source

LBNL

No news available for this project.