— Project Summary

Queue ID
APS-Q569
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

250 MW hybrid in Pinal, AZ · In queue since May 2024 · Proposed COD June 2028

250 MW

Capacity

1

Components

Solar

1y 10m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Impact Study25%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

32.732942, -111.566672 Milligan 230kV

Data Source

LBNL