BetaActiveSolarGasBatteryAPSLBNL
450 MW hybrid in Maricopa, AZ · In queue since May 2024 · Proposed COD December 2028
450 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Impact Study25%
Queue EntryMay 14, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Delaney 500 kV Substation via Q360 Gen-Tie
Data Source
LBNL
No news available for this project.