— Project Summary

Queue ID
APS-Q565
Capacity
161 MW
Technology
Wind
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveWindAPSLBNL

161 MW generation in Coconino, AZ · In queue since May 2024 · Proposed COD December 2025

161 MW

Capacity

1

Components

Wind

1y 10m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 7m

Schedule

3 months past proposed COD

Impact Study25%
Queue EntryMay 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Lat 35.373941, Long -111.515288

Data Source

LBNL

No news available for this project.