— Project Summary

Queue ID
APS-Q557
Capacity
75 MW
Technology
Solar+Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

75 MW hybrid in Navajo, AZ · In queue since May 2024 · Proposed COD June 2026

75 MW

Capacity

1

Components

Solar

1y 10m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 1m

Impact Study25%
Queue EntryMay 6, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Zeniff 69kV

Data Source

LBNL

No news available for this project.