BetaActiveSolarBatteryAPSLBNL
75 MW hybrid in Navajo, AZ · In queue since May 2024 · Proposed COD June 2026
75 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 1m
Impact Study25%
Queue EntryMay 6, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
AZ
County
Navajo
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Zeniff 69kV
Data Source
LBNL
No news available for this project.