200 MW storage in Pinal, AZ · In queue since May 2024 · Proposed COD March 2030
200 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Cluster Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 10m
Impact Study25%
Queue EntryMay 2, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-03-31
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Bianco 230 kV Substation East of Bianco Road, between Clayton Road and SR84 in Casa Grande