— Project Summary

Queue ID
APS-Q551
Capacity
700 MW
Technology
Solar+Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

700 MW hybrid in Coconino, AZ · In queue since April 2024 · Proposed COD May 2028

700 MW

Capacity

1

Components

Solar

1y 11m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Impact Study25%
Queue EntryApr 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Navajo 500 kV Switchyard

Data Source

LBNL