43.04 MW generation in Maricopa, AZ · In queue since April 2024 · Proposed COD April 2028
43.04 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Impact Study25%
Queue EntryApr 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Redhawk 500kV Switchyard
Data Source
LBNL
No news available for this project.