— Project Summary

Queue ID
APS-Q550
Capacity
43.04 MW
Technology
Gas
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveGasAPSLBNL

43.04 MW generation in Maricopa, AZ · In queue since April 2024 · Proposed COD April 2028

43.04 MW

Capacity

1

Components

Gas

1y 11m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

Impact Study25%
Queue EntryApr 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Redhawk 500kV Switchyard

Data Source

LBNL

No news available for this project.