BetaActiveDieselAPSLBNL
42.12 MW generation in Maricopa, AZ · In queue since April 2024 · Proposed COD June 2026
42.12 MW
Capacity
1
Components
Diesel
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 2m
Impact Study25%
Queue EntryApr 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
TSMC Fab 2 switchgear to Avery substation
Data Source
LBNL
No news available for this project.