499.5 MW generation in Coconino, AZ · In queue since September 2023 · Proposed COD December 2027
499.5 MW
Capacity
1
Components
Wind
2y 6m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 3m
Impact Study25%
Queue EntrySep 12, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
AZ
County
Coconino
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
APS Chevelon 345 kV Substation
Data Source
LBNL